Main Post SEIS Schedule
The Presidio Trust is amending their Management Plan (PTMP) with a draft Supplemental Environmental Impact Statement (SEIS). The document will consider proposed project alternatives on the Presidio Main Post, including the Presidio Museum and the Presidio Lodge. The SEIS schedule looks to wrap up the decision-making process in about six months. The timeline below is an estimate as of March 2008 and subject to change. source: Presidio Trust
June 2008 — Trust releases draft SEIS
June 2008 — 45-day public review process begins
July 2008 — Review process ends
August 2008 — Trust prepares final SEIS
September 2008 — Trust releases final SEIS
October 2008 — Trust prepares Record of Decision (ROD)
October 2008 — ROD signed